7 Step by Step Step by Step AOA Network Model Construction
 

Let’s have a project defined by a list of activities and their immediate predecessors (Task Dependency Table).

Activity (Task) Predecessors
A  
B  
C A
D A
E C,D
F B,E
G B
H G

 

Activities A and B have no predecessors, so they can begin immediately. However, Activity E can't start until both Activity C and Activity D have been completed and so on. Let's construct the AOA network for this project. Note, that you can't start an activity leaving a node until all of the activities entering that node have been finished.

Step 1: Let’s construct the first partial part of the project (exactly according to the task dependency table).

Each node represents an event, the starting or finishing of an activity. Node 1 is the project starting event. Node 2 is the event at which Activity A is finished. Activity A is Arc (1,2). Because the arc for Activity C begins at Node 2, Activity A must be finished before Activity C starts. There are two arcs connecting Nodes 2 and 4, corresponding to Activities C and D. You can't tell which activity Arc (2,4) represents. You can't have two arcs connecting a pair of nodes, so we introduce a dummy node to eliminate the confusion.
 
 

Step 2: Let’s construct the second partial part of the project introducing a dummy node.
 
 

The following picture shows the network after adding a dummy node, numbered Node 5. The dotted line from Node 5 to Node 4 represents a dummy activity that takes no time. The dummy activity's time, 0, appears on the arc. We introduced the dummy activity nodes to eliminate ambiguity. The new network still requires finishing A before starting C, finishing A before starting D, and finishing both C and D before starting E.

Step 3: Let’s construct the complete network of the project
 
 

Activity B be represented by an arc from Node 1 to Node 6. If it were, when Activity G's arc left Node 6, the network would require that both E and B be finished. But the precedence list requires finishing only B before starting G. Again, we introduce a dummy arc to give the correct precedence relationships (see following picture).


 
 

The complete AOA network model network model represents the precedence requirements for all activities in. We introduced two dummy arcs and a dummy node. Many times, you don't have to use dummy arcs or nodes.
 
 

Fortunately, when using project management software, you only input the list information and the software creates the network model. New professional software but mostly uses AON project network representation.